SP Timeline

CAYUSE SP IMPLEMENTATION TIMELINE

Tasks Timeline/Deadlines Status

Cayuse SP Central Staff Training December-January 2018 Complete

Grants Database: Awards Migration Spring-Summer 2018 Complete

Post-Award Module Development Spring 2018-TBD On schedule

Cayuse SP Routing Staff Training September-October 2018 Complete

Faculty and departmental staff training October-December 2018. Complete

Cayuse SP Initial Campus Launch October 3, 2018 Complete

Start Routing through Cayuse SP Fall 2018 Complete

Grants Database: Complete Migration Fall 2018 (by Dec. 31, 2018) Complete

Sunset Paper/Email Routing December 15, 2018 Complete

Cayuse SP Full Launch January 2019 Complete

Grants Database: Clean up Winter 2019 (Deadline TBD) On schedule

Post-Award Module Deployment TBD Will update